Atlas 5 launcher erected for MAVEN's launch to Mars
BY STEPHEN CLARK
SPACEFLIGHT NOW
October 11, 2013

United Launch Alliance on Friday began assembling the Atlas 5 rocket assigned 
to launch NASA's MAVEN mission in November and send the orbiter on a 10-month 
cruise to Mars to help decipher the red planet's thinning atmosphere.

The Atlas 5's bronze first stage traveled from a storage building at Cape 
Canaveral Air Force Station, Fla., to the Vertical Integration Facility 
at Complex 41 early Friday. Cranes hoisted the 106.6-foot-long first stage 
vertical and deftly placed the rocket atop the Atlas 5's mobile launch 
table.

Powered by an RD-180 main engine delivering 860,000 pounds of thrust, 
the first stage is known as the Common Core Booster. It houses tanks to 
hold 50,000 gallons of chilled liquid oxygen and 25,000 gallons of RP-1 
fuel, a highly refined variety of kerosene, for the RD-180 engine's four-minute 
burn to reach the upper atmosphere.

Technicians planned to add an interstage adapter before hoisting the Atlas 
5's Centaur upper stage atop the booster Monday, completing the build-up 
of the two-stage rocket.

The launch of NASA's Mars Atmosphere and Volatile Evolution, or MAVEN, 
mission only requires the most basic version of the Atlas 5 rocket. Called 
the "401" configuration, the Atlas 5 rocket for MAVEN features no solid 
rocket boosters, a Centaur stage with a single RL10 engine, and a four-meter 
payload fairing.

ULA can add strap-on boosters, a second RL10 engine and a larger five-meter 
nose shroud for payloads requiring the extra capability.

The launch of MAVEN will be the seventh Atlas 5 flight of the year, and 
the sixth from Cape Canaveral's seaside launch pad. ULA workers are in 
the final stretch of integrating and testing a Delta 4 rocket and its 
payload, a U.S. Air Force GPS navigation satellite, at Complex 37B for 
launch Oct. 23, less than 4 miles from the Atlas 5 rocket's launch pad.

Preparations for MAVEN's launch continue despite the partial shutdown 
of the federal government. After a two-day pause in the spacecraft's processing 
last week, NASA granted an exemption to resume work on MAVEN, which is 
in a time crunch to launch in a narrow window between Nov. 18 and mid-December.

Mars missions can only launch when the planets are properly aligned, and 
the next opportunity to launch MAVEN after December comes in early 2016.

But thanks to its exemption from the government shutdown, MAVEN is on 
schedule to launch Nov. 18 in a two-hour launch window opening at 1:28 
p.m. EST (1828 GMT).

The $671 million mission will reach Mars in September 2014, entering an 
elliptical orbit dipping into the outermost layers of the Martian atmosphere 
to sample its composition and measure its response to stimuli from solar 
activity.

Scientists hope MAVEN will address uncertainties in how Mars evolved from 
a planet with a warmer, thicker atmosphere with water into the barren 
world observed today.

Technicians from Lockheed Martin Corp., MAVEN's prime contractor, will 
load about 3,600 pounds of hydrazine fuel into the spacecraft's propellant 
tank Oct. 24. The Atlas 5's clamshell-like payload fairing will encapsulate 
MAVEN on Nov. 5, and workers plan to transport the Mars orbiter to the 
Atlas 5 launch pad Nov. 7 to top off the 19-story launcher. 